Clare Solar Farm

Clare Solar Farm is a 127 MW and comprising a large scale grid-connected photovoltaic (PV) solar plant including 68,540 piles and 393,000 solar panels.  The solar farm is located 35 kilometres south-west of Ayr in North Queensland.

SJA provided FVR with the following services;

  • Analysis and report on the contractors monthly status programs
  • Time-related review and assessments of extension of time claims
  • Independent expert report/forensic delay analysis – review and assess 12 extension of time claims
  • Independent expert report in relation to the cost of proposed rectification methodology for defective works.

SJA was closely involved in the client-side program management throughout the duration of the project providing the client with an independent review of the progress and forecasting of the onsite works.

SJA consistently identified undeclared program slippages through analysis of the contractor’s monthly status programs and provided the client confidence in relation to the actual status of the project.

Furthermore, SJA assisted with the assessment of time claims using the time impact analysis delay assessment method providing a high degree of accuracy.

Client
Fotowatio Renewable Ventures
Project Date
2017 – 2018
Location
North Queensland
Project Budget
$200 million