SJA Project Management was engaged by Pro-Invest Group for the delivery of a 239-bed hotel and mixed-use development in the Parramatta City Centre. Our team were instrumental in the lead up to early works DA lodgement, which required due diligence studies to inform transport, HV, sewer, contamination and archaeological constraints. Applications under the Heritage and National Parks and Wildlife Acts’ were prepared in advance to mitigate potential delay inherent to the historical and aboriginal archaeological programs.
SJA maintain several development programs for alternate critical path scenarios which assist the client with their feasibilities and forecast cash flows. The schematic design phase required us to manage a skilful and focused team of over 20 disciplines. The team was able to navigate the myriad of legislation and produce a quality design outcome for our client and a main works DA lodgement in July 2019.