Australia
Recent fuel escalation – driven by geopolitical instability in the Middle East and tightening conditions across global oil supply markets is now having a more tangible impact on construction delivery. This pressure is now amplified given 80-90% of Australia’s liquid fuel is imported. [1].
With diesel prices increasing significantly over a relatively brief period, peaking around AUD $2.76 / litre, resolving back to the current average of AUD $2.39 / litre (which remains approximately 47% higher than pricing for the same one year ago) are no longer able to be absorbed and cost increases being passed down the line [2]. This is not a marginal fluctuation. It is becoming an increasingly important input affecting how projects are priced, procured, and delivered, including within the wider context of macro-economic considerations inclusive of cost-of-living increases, inflation rates and wage pressure.
Fuel is no longer simply a stable background cost within construction. Fuels and associated petrochemical products are increasingly acting as a primary cost input influencing price rises for materials, logistics and subsequently programme concurrently.


A structural shift in cost drivers
The construction sector’s exposure to fuel costs is both direct and indirect. Diesel cost increases are impacting daily site activities such as earthworks, piling, cranage and temporary power.
Supply chain impacts are also prevalent with the wider supply chain as opposed to direct consumption. For example, Reece Australia has indicated price increases of up to 26% on plastic pipes due to disruptions in oil and resin supply.
According to Rawlinsons Market Insight (April 2026), these pressures are being passed through rapidly, with limited capacity for contractors to absorb costs within existing margins. The report highlights widespread escalation across materials such as bitumen, asphalt, steel, aluminium, concrete, quarry products, timber, glazing systems and plastic-based products like PVC and HDPE pipework – all of which are sensitive to energy inputs and use of petrochemical derivatives in manufacturing processes.
As a result, fuel and energy volatility is influencing not only transportation costs but also the underlying price of materials as well as the overall inflationary macro-economic circumstances. This omnipotent exposure across production and delivery and the wider economy means cost increases can accumulate progressively across projects rather than appearing as a single identifiable movement. In response, the market is increasingly embedding fuel-related adjustments into pricing through surcharges or revised base rates.
Where the pressure is emerging in projects
At a project level, these impacts are rarely experienced as a single discrete event. Rather, they tend to emerge progressively through a series of incremental changes across trades, procurement packages and delivery conditions. Collectively, these movements influence the overall commercial position of a project.
Rawlinsons’ April 2026 Market Insight, which featured a dedicated “fuel crisis” theme, examined how rising fuel costs are flowing through to the construction sector. The report identifies three primary transmission mechanisms: increased operating costs (particularly for diesel-powered plant, equipment and site vehicles), higher transport and logistics costs (affecting materials, components and services) and direct upward pressure on building material prices [5].
Concurrently, pricing volatility is becoming more pronounced. Supplier quotations are increasingly being held for shorter durations, and pricing is more frequently subject to review where input costs remain uncertain. As a result, procurement strategies are having to adapt to a more dynamic and less predictable purchasing environment.
These challenges are further compounded by broader supply chain factors. Ongoing geopolitical tensions affecting key global shipping routes, including the Strait of Hormuz, underscore the vulnerability of construction supply chains to external disruption. In parallel, evolving government responses – such as the Fuel Cost Recovery Order – may provide avenues for partial cost recovery, but also introduce additional layers of commercial complexity [6].
In practical terms, the combined effect is one of sustained cost pressure alongside potential supply constraints. The extent to which these factors influence project pricing and programme will vary depending on project-specific circumstances, but the overall risk profile is clearly elevated.
Translating market movement into project impact
Trading Economics reported that Australia’s annual inflation increased to 4.6% in March 2026, up from 3.7% in the previous month. Goods inflation also rose to 5.5% from 3.5% in February, largely driven by higher transport costs associated with rising fuel prices [7].
Assessing the extent of fuel-related escalation requires more than a single-point adjustment. The impact typically does not sit in isolation within a single trade, cost category, or index. Rather, it manifests across multiple areas, including plant, materials and logistics and may also have consequential effects on the construction programme.
In practice, this is best understood through observed movement over time. This involves comparing original cost allowances and escalation assumptions against current supplier pricing, historical tender returns, revised submissions and prevailing market rates. Such a layered assessment is often necessary to establish a reliable view of cost movement at the project level.
In parallel, cargo restrictions arising from instability in the Middle East have the potential to affect project programmes. Where material availability or delivery timelines are disrupted, procurement sequencing may be impacted, with flow-on effects for programme delivery. The extent of these impacts will, however, vary depending on project-specific circumstances.
Other imperatives may result in the risk of longer holding and storage of materials and stock in order to protect against scarcity or volatility of availability and certainty of delivery in relation to various categories of commodities.
Establishing a robust, causally linked analysis depends on both the availability and completeness of supporting information. Strong conclusions are generally underpinned by contemporaneous records that clearly connect changes in market conditions to supplier responses and resulting project impacts. Relevant information sources may include supplier quotations, freight and fuel-related adjustments, historical rate benchmarks and broader market indices across fuel, petrochemicals, metals and plastics, supported by procurement and programme records where applicable.
Commercial management and substantiating impact
As fuel-driven cost pressures become increasingly embedded across construction delivery and the broader economy, attention is shifting toward how projects manage and substantiate change in real time.
In practice, this is less about relying on formal dispute mechanisms and more about maintaining disciplined contract and cost management throughout project delivery. Central to this approach is the ability to clearly demonstrate the relationship between external market movements and resulting project impacts, thereby preserving commercial clarity between parties.
This typically involves the consistent monitoring of changes in supplier pricing, freight and logistics costs and material price movements. Increasingly, contemporaneous records are being relied upon to establish a transparent view of how evolving market conditions are translating into project outcomes.
From a practical perspective, the robustness of any assessment is not determined by a single document or data point. Rather, it is derived from a combination of supporting information sources. These may include supplier correspondence evidencing price changes, updated quotations, cost plan revisions and relevant market indices for key inputs such as fuel, metals and plastics.
When applied effectively, this approach enables projects to demonstrate a clear and logical progression from market conditions through to procurement response and final cost outcomes. This, in turn, reduces ambiguity and supports more structured and informed commercial decision-making as projects navigate periods of volatility.
Positioning for response
What is emerging is not simply an increase in costs, but a broader shift in how fuel-related risk is understood and managed within construction delivery.
Where such risk was once largely implicit, it is now more explicitly recognised, assessed and in many cases, reflected in pricing and procurement strategies. This shift is influencing market behaviour, with project participants placing greater emphasis on risk allocation during procurement and articulating these considerations more clearly in commercial discussions.
The level of exposure will continue to vary depending on factors such as contract structure, procurement timing and supply chain composition. However, the overarching trend suggests that fuel-related inputs are becoming a more visible and defined component of both project cost and risk.
The key challenge lies not only in identifying cost movement, but in understanding how these movements develop, where they sit within the project structure and how they can be demonstrated in a clear, structured and supportable manner.
SJA continues to support projects in addressing this challenge by combining market insight with detailed technical cost analysis. Our experience spans the application of mechanisms such as fuel adjustment clauses, provisional sums and indexed escalation formulas linked to recognised fuel benchmarks.
This approach enables project teams to account for fuel-related fluctuations at both tender stage and during delivery, improving pricing realism and reducing the likelihood of disputes. It also supports more sustainable commercial outcomes – either by minimising the need to recover unforeseen costs on future projects or by providing robust, evidence-based analysis to substantiate claims for adjustments to the contract sum and extensions of time on current projects.
SJA welcomes the opportunity to share practical insights and discuss how these learnings may be applied to your projects.
References
[1] National Roads and Motorists Association – Australia fuel supply chain facts https://www.mynrma.com.au/open-road/news/2026/australia-fuel-supply-chain-facts
[2] Global Petrol Prices – Fuel price data https://www.globalpetrolprices.com/Australia/diesel_prices/
[3] Australian Financial Review – https://www.afr.com/companies/infrastructure/reece-pushes-36pc-price-rise-on-plastic-pipes-in-building-cost-shock-20260324-p5ts6x
[4] Rawlinsons Market Insight April 2026 – https://cdn.prod.website-files.com/689adaa3591e818857fbcb14/69e0563ee082197a64a5fdee_Market%20Insight%20-%20April%202026%20-%20Compressed.pdf
[5] Rawlinsons Market Insight April 2026 – Fuel Crisis – https://cdn.prod.website-files.com/689adaa3591e818857fbcb14/69dd81e082074c8a50d18f38_Market%20Insight_Fuel%20Analysis_April%202026%20(2).pdf
[6] Piper Alderman – Fuel cost recovery order lands: what principals and contractor must do now – https://piperalderman.com.au/insight/fuel-cost-recovery-order-lands-what-principals-and-contractors-must-do-now/
[7] Trading Economics – Australia Inflation Rate https://tradingeconomics.com/australia/inflation-cpi